Timeline
-
2027 Skandia Gateway is finished. The fairway is deepened and the western quay is ready.
-
December 2027
-
In 2027 the fairway will be deepened and ready.
-
-
May 2026
-
Dredging by the west quay is estimanted to be ready during the second quarter of 2026.
-
-
October 2025
-
Contractor west quay finished.
-
-
August 2025
-
Deepening and widening of the fairway has a planned start. Dredging started.
-
-
November 2022
-
Agreed national cost, NCC to begin construction.
-
-
June 2022
-
Main hearing of environmental permit is held between June 1 and June 3.
-
-
May 2021
-
When the depth of the fairway is three-four meters deeper, all vessels that carry more than 5000 containers will be able to carry a bigger load.
-
-
December 2020
-
A permit application, together with the environmental impact assessment, was submitted for examination by the Land and Environment Court on 22 December 2020.
-
-
June 2018
-
The government decided on a national infrastructure plan spanning through 2018-2029 whereas 1,25 billion SEK will go towards deepening the fairway in the port of Gotenburg.
-
-
2017January
PROJECT STARTING